Question: NEC '11Dedicated Equipment Space 110.26(E)(1)(a) & (b)(a) seems to say that no leak protection apparatus shall be located in the zone but(b) states Foreign Systems may be allowed provided that leak protection is installed.Do I read this as I would my PLC programming in that the last instruction always takes precedence?

Yes, (b) takes precedence over (a).In NEC 110.26(E)(1)(a), it states that "No leak protection apparatus shall be located within the zone." This means that if you have a leak protection device, it should not be placed inside the dedicated equipment space.However, in NEC 110.26(E)(1)(b), it states that "Foreign Systems may be allowed provided that leak protection is installed." This means that if you have a foreign system, such as a pump or a compressor, you can install it in the dedicated equipment space, but you must also install leak protection.Therefore, the answer to your question is yes, you can read this as you would your PLC programming in that the last instruction always takes precedence. In this case, (b) takes precedence over (a), so you can install a foreign system in the dedicated equipment space if you also install leak protection. Flag for review

Previous Question Next Question