Question: So, here is a copy of an e-mail I received requesting an Estmate:"I am looking for best price available. Electrical work as per below: Install a 120volt sub panel in the unfinished area using the existing SEU cable for furnace, refeed furnace Basement Office: Add (3) AFCI protected receptacles Basement Office Closet: Add wiring for (1) fixture with (1) switch and AFCI protection. Customer will provide fixture. Unfinished Area: Add (1) 20amp120volt GFCI circuit for freezer and (1) 20amp/120volt GFCI receptacle for the sump pump"If they indeed want a sub using the SEU does it not appear that all of the additions would be on one circuit? I have not seen the SEU yet but this just does not look right. Any thoughts?
Yes, it is possible that all the additions would be on one circuit if they are using the existing SEU cable for the furnace to install the 120-volt subpanel. However, without seeing the SEU cable and evaluating its capacity, it is difficult to determine if this is a viable option.
Possible Issues
Overloading
The SEU cable may not be rated to handle the additional load of the new circuits, especially if the freezer and sump pump are operating simultaneously.
Voltage Drop
The length and size of the SEU cable could cause significant voltage drop, affecting the performance of the appliances and fixtures.
Code Violations
Using a subpanel on an existing circuit without proper grounding and protection may be a code violation.
Recommended Approach
Inspect the SEU Cable
Examine the SEU cable to determine its size, length, and condition. Verify if it is suitable for the intended use.
Calculate Load Requirements
Determine the total amperage of all the appliances and fixtures that will be connected to the subpanel.
Check Code Compliance
Ensure that the installation meets all applicable electrical codes, including grounding, protection, and circuit capacity requirements.
Alternative Options
If the existing SEU cable is not suitable for the subpanel, consider the following options:
Install a New Subpanel with Dedicated Feed
Run a new circuit from the main electrical panel to the subpanel to provide a dedicated power source.
Increase Circuit Capacity
Determine if the existing circuit can be upgraded to accommodate the additional load. This may involve replacing the circuit breaker or upgrading the wiring.
Communication with Client:
It is important to communicate these concerns with the client and discuss the viable options to ensure a safe and compliant electrical installation. Flag for review