Question: The only panel change-out I have done I did in this manner:Identified and labeled all circuits.Had the POCO pull the meter.Used a generator for lights, receptacles, etc.Removed old panel(fuse panel)Installed new breaker panelInstalled conductors and breakers and labelWait for inspectionHave POCO reinstall meter.This was simple because there was no one living in the house and the panel size, 200A, was the same, no change in the SE conductors. My question is, how do you guys handle a change-out like this? And how do you change one when there are people living in the house? Also, how do you figure charges for the time it takes to identify each circuit when they are not marked or marked very well?Thanks!

Panel Change-Out Process with Tenants

1.

Schedule and Communicate

Schedule the change-out during a time that minimizes inconvenience for tenants. Inform tenants of the work and its potential impact on utilities.2.

Identify and Label Circuits

Identify all active circuits and label them clearly for easy reconnection. If circuits are not marked, use a circuit tracer or continuity tester to identify them.3.

Generator Setup

Install a generator outside the house to provide temporary power for essential appliances, lighting, and refrigeration.4.

Temporarily Disconnect Old Panel

With the generator in place, disconnect the main breaker and all branch circuits of the old panel. Secure them for safety.5.

Remove Old Panel

Remove the old panel from its location.6.

Install New Panel

Install the new breaker panel in the same location as the old one, ensuring proper grounding and electrical clearances.7.

Install Conductors and Breakers

Install the SE conductors and connect them to the main breaker. Install individual breakers for each identified circuit.8.

Rewire Circuits

Reconnect each labeled circuit to the appropriate breaker in the new panel.9.

Inspect and Test

Inspect all connections and conduct circuit testing to verify proper operation.10.

Re-Energize

Turn on the main breaker and restore power to the house.11.

Inform Tenants

Inform tenants that power has been restored and answer any questions they may have.

Charging for Circuit Identification



Estimate Time

Estimate the time it will take to identify each circuit based on the size of the panel and the markings available.


Flat Rate

Charge a flat rate for circuit identification, regardless of the actual time taken.

Hourly Rate

Charge an hourly rate for circuit identification, billed in increments (e.g., 15 minutes or half-hour).

Additional Considerations



Safety

Ensure all electrical work is performed by a qualified electrician.

Permits

Obtain all necessary permits from the local building department.


Meter Reinstallation

Coordinate with the POCO to reinstall the meter once the new panel is operational.*

Cleanup:
Clean up the work area thoroughly after the change-out is complete. Flag for review