Topic: "Line side" tap on sub panel for PV installation possible?

User: ggunn, Location: Austin, TX, USA

Asked on: Wednesday, March 2, 2011 at 11:57 am EST
Answered on: Tuesday, May 14, 2024 at 2:16 am EDT

Question: We have a customer who wants to install a substantial amount of PV on a ranch. The ranch is on a single meter with a 400A main feeding several subpanels and the PV inverter would be located at one of the subs. The question that has been posed to me is if we can tap into the line feeding the subpanel from the main because the PV will not fit into it on a backfed breaker under the 20% rule. I'm not at all sure what the ramifications of such a connection strategy would be. It would, for one thing, change the breaker feeding the sub into a backfed breaker; would the size need to change? What about wire size from the main to the sub?It seems to me that the correct way to do this would be to upsize the subpanel and replace its main breaker with the current sub main breaker to make room for the PV, but I have been asked to investigate this approach.

Ramifications of Tapping into Line Feeding Subpanel



Safety Concerns

Tapping into a live line is hazardous and should only be performed by a qualified electrician. Proper isolation and safety precautions are crucial.


Electrical Code Violations

NEC 705.12 requires PV systems to be installed according to the manufacturer's instructions. Tapping into a line without proper authorization may violate this code.

Impact on Breaker

Backfeeding the subpanel breaker will change its function and may require upsizing. The new breaker must be rated for the combined load of the subpanel and the PV system.


Wire Size Considerations

The wire size from the main to the subpanel may need to be increased if the load is significantly increased by the PV system.

Voiding Manufacturer's Warranty

Tapping into the line may void the warranty of the subpanel or the PV inverter.


Future Maintenance and Troubleshooting

Accessing the tapped line in the future could be challenging, especially if the subpanel is fully loaded.

Recommended Approach

To ensure safety, code compliance, and long-term reliability, it is

strongly recommended
to upsize the subpanel and replace its main breaker with the current sub main breaker. This will provide sufficient space for the PV inverter and meet all applicable electrical codes.

Steps for Upsizing Subpanel:1. Turn off power to the subpanel.
2. Install a larger subpanel with the same or higher amperage rating as the main panel.3. Transfer the original sub main breaker and other existing circuits to the new subpanel.
4. Install the PV inverter into the new subpanel.5. Re-energize the subpanel and verify proper operation.This approach will ensure a safe and code-compliant installation, minimize potential hazards, and maintain warranty coverage for all equipment involved. Flag for review