Question: Industrial setting in a theater, like a CircDu Solei building, (as a reference for the type not that actual building). I have a motor and blower assy that is attached to a metal frame. No bonding is in place. The metal frame is constructed using unistrut and standard unistrut connections and fittings with nuts and bolts. The frame work was constructed in a box style with several braces and cross braces so it could also mount the control cabinet on.My question is do I need to bond each location where the unistrut connectors are, and if so do i need to drill and tap them?

Bonding Requirement

According to the National Electrical Code (NEC), equipment grounding conductors (EGCs) must be provided for all metal raceways, enclosures, and equipment that may become energized. This includes metal frames and other conductive materials that could potentially carry current.

Bonding of Unistrut Connections

Unistrut connectors are typically made of galvanized steel, which is a conductive material. Therefore, it is generally recommended to bond all unistrut connections to maintain electrical continuity and ensure proper grounding.

Drill and Tap Method

One method for bonding unistrut connections is to drill and tap the connectors. This involves creating a threaded hole in the connector and installing a grounding screw or a grounding lug with a grounding conductor.

Alternative Bonding Methods

In some cases, it may be possible to use alternative bonding methods such as:

Grounding clamps

Clamps that can be attached to the unistrut without drilling or tapping.


Conductive adhesive tape

Adhesive tape that has conductive properties and can be used to bond the connectors together.

Solder bonding

Soldering the connectors together, which creates a permanent electrical connection.

Recommendation

Based on the information provided, it is recommended to bond the unistrut connections in the metal frame using the drill and tap method. This ensures a reliable and secure electrical connection that meets the safety requirements of the NEC.

Additional Considerations:
The grounding conductor size should be determined based on the equipment and circuit requirements. The grounding conductor should be properly connected to the equipment grounding system. It is important to use a corrosion-resistant grounding conductor and hardware. Flag for review