User: Mark Patterson, Location: Three Lakes Wi
Asked on: Friday, March 11, 2011 at 12:57 pm EST
Answered on: Tuesday, May 14, 2024 at 2:40 am EDT
Question: I just went to a 2011 code update class and they were taling about having too run 3 nuetrals with a eq. ground when we have working with 208 three phase instead of just running 1 neutral with every three phases of the 208. Is this right.
Yes, the 2011 NEC requires three neutral conductors with an equipment grounding conductor for 208Y/120V three-phase electrical systems. This is different from the previous code, which only required one neutral conductor for every three phases.
Reason for the Change
The 2011 NEC change was made to address concerns about neutral overload and unbalanced loads. With only one neutral conductor, there was a potential for overloads on the neutral if one of the phases was heavily loaded. This could lead to overheating and potential fire hazards.
New Requirement
The new NEC requirement mandates that three neutral conductors be run with an equipment grounding conductor for 208Y/120V three-phase systems. This ensures that each phase has its own dedicated neutral conductor, reducing the risk of neutral overload and providing a more balanced load distribution.
Exceptions
There are some exceptions to this rule, such as: When only linear loads are used (e.g., lighting) When the system is delta-connected (instead of Y-connected)* When a derived neutral is acceptable (e.g., for motor loads)
Implications for Electricians:
This change impacts electrical installations by requiring additional neutral conductors to be run. Electricians need to be aware of this requirement and ensure that their installations comply with the NEC. It may also increase the cost of materials and labor for electrical contractors. Flag for review