Topic: Lighting retrofit

User: ASK_EDDIE, Location: TEXAS

Asked on: Friday, March 11, 2011 at 10:11 pm EST
Answered on: Tuesday, May 14, 2024 at 2:42 am EDT

Question: Like a lot of things, Ive done the work but never bid one for my own company.I have a building with 530 8 ft strips to be retro fitted to double 4 fts my costis 28 dollars a fixture and 1.38 per lamp. 1100.00 for 8ft lamp disposal, 1000.00 for lift rental , 500, for wirenuts ect. i did a test fixture it took an hour..... i know it can be done in 20 minutes with 2 people on the lift and a ground person in an operational store with customers and shelving and store product and 15ft ceiling slowing you down at every turn. I gave a price of 47,000 and the guy choked and died over the phone. am out of the ballpark ?

Calculation

Fixture cost: 530 fixtures x $28/fixture = $14,840 Lamp cost: 530 fixtures x 2 lamps/fixture x $1.38/lamp = $1,474.60 Disposal cost: $1,100 Lift rental: $1,000 Wire nuts: $500Total cost: $19,914.60

Estimated Labor Cost

Test fixture time: 1 hour Estimated operational time: 20 minutes/fixture x 530 fixtures / 2 people = 2,650 minutes = 44.17 hours

Labor Cost Calculation

Assuming a labor rate of $50/hour: 44.17 hours x $50/hour = $2,208.50

Total Bid Calculations

Material cost: $19,914.60 Labor cost: $2,208.50 Overhead and profit margin (typically 15-25%): $4,417.05 - $5,521.38

Total Bid Range

$26,540.15 - $28,034.53

Assessment

Your original bid of $47,000 is significantly higher than the calculated range of $26,540.15 - $28,034.
53. This suggests that you may have overestimated your labor costs or overhead. The customer's reaction indicates that your bid was not competitive.


Recommendations:
Consider reviewing your labor estimates and ensuring they are realistic. Break down your costs in detail to identify any areas where you can reduce expenses. Research similar projects to understand industry benchmarks for labor and overhead costs. Be prepared to negotiate and adjust your bid based on market conditions and customer requirements. Flag for review