Question: Hi Mike, I have been advised that one of the changes for the 2011 NEC is that all medium voltage splices and terminations must be performed by factory certified contractors. Is this true?
Yes, this is true. The 2011 NEC requires that all medium voltage splices and terminations must be performed by factory certified contractors. Flag for review