Question: I have a job were I have to install about 3K feet of 3/4" emt on a roof. This appears to be a fairly easy install. Attached to brick approx 3 feet off of roof, then along rooftop on stand-offs and attached to HVAC units. Can anyone advise how many man-hours to charge per x feet of conduit? Thanks.

Factors to Consider

Complexity of the route (straight runs vs. bends and offsets) Height and accessibility of the installation Number of stand-offs and HVAC units for attachment Labor rates and overhead costs

Estimated Man-Hours per 100 Feet of Conduit



Straight runs

1.5 - 2.5 hours


Bends and offsets

2.0 - 3.5 hours

Elevated or difficult access

Add 0.5 - 1.0 hour per 100 feet

Total Estimated Man-Hours for 3K Feet of Conduit



Straight runs

3,000 feet / 100 feet 2 hours = 60 hours

Bends and offsets

Assuming 25% of the route requires bends and offsets: 3,000 feet x 0.25 = 750 feet 750 feet / 100 feet 3 hours = 22.5 hours

Elevated or difficult access

Assuming 15% of the route is elevated or difficult to access: 3,000 feet x 0.15 = 450 feet 450 feet / 100 feet 0.75 hour = 3.38 hours

Total

60 hours + 22.5 hours + 3.38 hours =

85.88 hours
Recommended Charge Rate

Multiply the estimated man-hours by your hourly labor rate, plus any applicable overhead costs.

Example

Labor rate: $50 per hour Overhead: 20% Total charge rate: $50 x 1.2 = $60 per hour* Total cost: 85.88 hours x $60 =

$5,152.80