User: lielec11, Location: Charlotte, NC
Asked on: Tuesday, June 10, 2025 at 10:29 am EDT
Answered on: Tuesday, June 10, 2025 at 10:30 am EDT
Question: We have a system where three (3) 2000kVA gensets are paralleled onto a common switchgear. When we run our fault calculations in SKM we assumed all generators are running at the time of a fault. Therefore at the time of a fault, as a rotating machine, each generator will contribute fault to the system for a short period of time like a motor would. We submitted our report as such showing the three (3) generator mounted breakers (NOT on the paralleling gear) failing because the combined fault current from all three gensets is greater than the AIC of the breakers (100k). The gear itself is fine as it is rated 200kA.Here is where we disagree with the EOR on their response back. They are trying to direct us to run the fault calculations for the generator breakers as if the fault itself is isolating one generator from the system. They're claiming that the genset breakers will only see contribution from the OTHER two gensets at the time of a fault.I disagree because if there is a fault when all three gens are running, all three will contribute fault current to that device. I understand that if there is a fault at one of these breakers it will isolate one generator from the rest of the system, but it will still contribute fault current to the main CB in question. Therefore, the fault current MAY be to high for the breaker to actually isolate the fault as intended.Does this make sense? Am I a moron?
You are absolutely not a moron. Your understanding of fault current contribution from paralleled generators is correct. The EOR's logic is flawed and potentially dangerous. Here's a breakdown of why
Your Reasoning is Sound:
Initial Fault Contribution
When a fault occurs while all three generators are running, all three generators will initially contribute fault current. This is due to the stored energy in the generators' rotating mass and magnetic fields. This initial contribution is what determines the required interrupting rating (AIC) of the generator breakers.
Breaking Time vs. Fault Contribution Decay
The EOR's argument seems to imply that the breaker opens before the faulted generator contributes significant current. This is not how it works. Breakers take time to operate (typically cycles, not instantaneous). During that time, the faulted generator is actively contributing fault current.
Breaker Rating Focus
The AIC (Ampere Interrupting Capacity) rating of a breaker dictates its ability to interrupt the fault current. It is critical to ensure that the calculated fault current (taking contributions from all generators into account) is less than the breaker's AIC rating. Exceeding the AIC rating can lead to breaker failure, catastrophic damage, and potential personnel hazards.
Selective Coordination & Cascading
If the generator breaker is not rated to interrupt the fault current, it may not operate properly or at all. This can lead to cascading failures, where upstream devices (like the main switchgear breaker) are forced to interrupt a fault current beyond their designed capability.
Why the EOR's Logic is Flawed
Assuming Instantaneous Isolation
The EOR's logic assumes the generator breaker somehow instantaneously disconnects the generator from the system before it contributes fault current. This is physically impossible. Breakers have operating times, and fault current contribution is nearly instantaneous.
Misunderstanding of AIC
The EOR seems to be treating the breaker rating as a continuous current rating or as some kind of 'limiter'. The AIC rating is about the breaker's ability to interrupt the high fault current safely.
How to Properly Analyze the Situation
SKM Fault Study
You've correctly run the SKM fault study assuming all generators are online. This is the conservative and correct approach for determining the required AIC rating of the generator breakers.2.
Momentary vs. Interrupting Duty
SKM (and other power system software) typically calculates both momentary and interrupting duty currents. The interrupting duty is what matters for AIC rating of breakers. Make sure you're comparing the interrupting duty fault current against the breaker's AIC.3.
Review Breaker Operation Times
Double-check the breaker's published operating time (total clearing time, including relaying and breaker opening). This will confirm that significant fault current contribution will occur before the breaker trips.4.
Selective Coordination Study
A proper selective coordination study should be conducted to ensure that the generator breakers trip before the main switchgear breaker for faults close to the generators. This is crucial for minimizing the extent of the outage and preventing cascading failures.
What You Should Do
Documentation
Document your calculations clearly, showing the fault current contribution from all three generators at the generator breaker locations.2.
Communication
Communicate your concerns clearly and professionally to the EOR, explaining the reasons why their approach is incorrect. Use the arguments I've outlined above.3.
Code References
Cite relevant code references (e.g., IEEE standards, NEC articles) that support your position. For example, the NEC requires that breakers be rated to interrupt the available fault current at their terminals.4.
Escalate if Necessary
If the EOR refuses to acknowledge the issue, escalate the concern to a higher authority within your organization or theirs. This is a serious safety issue that needs to be addressed.5.
Consider a Third-Party Review
If necessary, suggest a third-party review by a qualified power systems engineer to resolve the disagreement.
In summary, you are correct. The generator breakers must be rated to interrupt the fault current contributed by all three generators. The EOR's approach is flawed and could lead to a dangerous situation. Stand your ground and advocate for a safe and properly engineered system. Flag for review